On the South Ukrainian nuclear power plant CREWE revealed violations for the sum of 81 million UAH

Online: {{ reading || 0 }}Read:{{ views || 1807 }}Comments:{{ comments || 0 }}    Rating:(1084)         

Control - by auditing management in the Nikolaev area in April of the current year audit of the Separated division "South Ukrainian nuclear power plant" by DP NAEK "Energoatom" from 01.01.2007 is complete till 31.12.2007. Audit established financial violations for total amount over 81млн. UAH. About it reports a press - service CREWE in the Nikolaev area.

In particular, YuU nuclear power plant, despite of carrying out indexation of fixed assets, didn't initiate a question before Regional office of Fund state, concerning revision of the size of a rent. As a result the lease contracts which have been directly concluded by the most nuclear power plant weren't revised. It led to short-reception of the nuclear power plant of the income in the sum 2,1млн. UAH and the state budget - 1,5 million UAH

In the auditing period by station it is carried out payment to commercial structures of means for proyektno - design documentation, scientifically - technical production and the performed works for the sum of 31,3 million UAH of receipt and which performance it isn't documented.

For violation of conducting accounting on 6 officials of YuU nuclear power plant protocols on administrative offenses are made.

Materials of audit of the Separated division "South Ukrainian nuclear power plant" are sent to GLAVKRU of Ukraine for inclusion to the general act of audit of DP NAEK "Energoatom".

-