It is southern - the Ukrainian nuclear power plant was ahead of schedule electric power developments for 2008

Online: {{ reading || 0 }}Read:{{ views || 1224 }}Comments:{{ comments || 0 }}    Rating:(734)         

In December in OP "It Is Southern — the Ukrainian Nuclear Power Plant" it was developed 1 billion 543 million 126 thousand kilowatts - hours of the electric power, and the nuclear power plant rated capacity efficiency (RCE) in a month made 68,08%. The plan for December was implemented by this enterprise for 101,4%, reports a press - service Is southern - the Ukrainian nuclear power plant.

In total for 2008 the nuclear power plant developed 19 billion 259 million, and since the operation beginning, that is since December, 1982 - 402 billion 515 million kilowatts - hours of the electric power. KIUM indicator for last year made 73,08%. The annual plan of development of the electric power It is southern - by the Ukrainian nuclear power plant it was exceeded and I made 101,4%.

The equipment of the first and second power units within December worked without remarks in the set mode, and already on December 22, after the end of repair, the third power unit was connected to a power supply system of Ukraine also.

On Aleksandrovsky hydroelectric power station in work there were first and second hydrounits (depending on a consumption of water in the river the Southern Bug). In total for the specified period electricity generation made 4 million 505 thousand kilowatts - hours. For 2008 on AGES 45 million 32 thousand, and since the operation beginning (April, 1999) - 220 million 498 thousand kilowatts - hours of the electric power are made.

The first and second hydrounits of Tashlyksky pumped storage power plant within December worked according to the established schedule. The second hydrounit was from December 1 to December 7 in planned repair. Electric power development for the period made 19 million 82 thousand kilowatts - hours of the electric power. For 2008 electricity generation on TGAES made 231 million 675 thousand, and since the operation beginning (October, 2006) of 401 million 821 thousand kilowatts - hours.

Radiation background at an industrial site It is southern - the Ukrainian nuclear power plant in December, 2008, according to measurements, I was at the level of the natural background values measured still before start-up of nuclear power plant, and for January 8, 2009 I made 12,1 μR/hour. As for emissions of radioactive materials in environment, they don't exceed the established admissible values.

-