The deputy minister of fuel and power industry of Ukraine paid attention on Is southern - the Ukrainian nuclear power plant

Online: {{ reading || 0 }}Read:{{ views || 812 }}Comments:{{ comments || 0 }}    Rating:(487)         

The other day meeting of a special staff under the leadership of the deputy minister of fuel and power industry of Ukraine of Natalya Shumkova took place. Representatives of Ministry of Fuel and Energy, NAEK management participated in meeting, Is southern - the Ukrainian power complex, design and contract organizations.

Participants of a staff, besides a question of completion of Tashlyksky pumped storage power plant, discussed also a course of implementation of the project which is realized on Is southern - the Ukrainian nuclear power plant - reconstruction of system of technical water supply of nuclear power plant. Its main objective - increase of cooling ability of a pond - a nuclear power plant cooler. The project assumes construction of 5 additional sprinkling pools and pump station.

This project is 2 of 7 defined by the company in the list of large infrastructure projects which need to be realized in a prime order. Unfortunately, and in this case didn't do without problem questions. The declared company - the producer of the pump equipment couldn't fulfill the obligations therefore it is planned to carry out work on return of advance payment and carrying out soon the new tender by firm definition - the manufacturer, reports work Department with the public and mass media Is southern - the Ukrainian nuclear power plant.

Reconstruction of system of technical water supply of YuU nuclear power plant is provided "By the program of reduction of losses of development of the electric power for temperature and quality of circulating water on YuU nuclear power plant". Full completion of works on reconstruction of system of technical water supply of the nuclear power plant was planned on 2011-й year. Implementation of the project will provide optimum operating conditions of 3-x nuclear power units during the whole year.

Today deficiency of cooling ability of a pond - a nuclear power plant cooler in hot summer months makes 1200 MWt. Over the last 10 years works of nuclear power plant on this reason over 6 billion kilowatts - hours of the electric power are underproduced. It is more indicator of average annual production of one nuclear block.

Works on construction of the sprinkling pools are begun last year, but from - for lack of financial means were suspended.

-