The court initiated proceedings on bankruptcy of the general contractor of construction of Tashlyksky pumped storage power plant

Online: {{ reading || 0 }}Read:{{ views || 909 }}Comments:{{ comments || 0 }}    Rating:(545)         

The economic court of the Nikolaev area opened on June 1, 2009 proceeding of bankruptcy of JSC Yuzhenergobud (Yuzhnoukrainsk, the Nikolaev Region), a general contractor of a construction of Tashlyksky hydroheat-sink power plant.

As it is reported in the official announcement in the press of June 6, claims of creditors and the statement of sanator are accepted within a month from the date of its publication.

As of February, 2009 a number of natural persons was concentrated by 70,848% of the stocks "Yuzhenergobuda", another 13,743% of actions belonged JSC Stroypolis Insurance Company (Kiev).

The Tashlyksky pumped storage power plant is under construction on the river the Southern Bug in the Nikolaev area. The station enters in Is southern - the Ukrainian power complex which unites Is southern - the Ukrainian nuclear power plant (nuclear power plant) and the Aleksandrovsky small hydroelectric power station (hydroelectric power station) constructed on the bottom reservoir of pumped storage power plant.

The starting complex of Tashlyksky pumped storage power plant turns on two hydrounits total rated capacity in a turbine mode of 302 MWt, in the pump - 454 MWt. The first hydrounit of pumped storage power plant was put into operation in August, 2006, and the second - in July 2007-го.

The customer of construction of power plant NAEK "Energoatom", the operator of all four operating nuclear power plants of Ukraine, as a general contractor - "Yuzhenergobud"