It is southern - the Ukrainian nuclear power plant was ahead of schedule on electricity generation

Online: {{ reading || 0 }}Read:{{ views || 689 }}Comments:{{ comments || 0 }}    Rating:(413)         

According to operational data of Mintoplivenergo, from January till September the Ukrainian nuclear power plants developed 60,522 billion kWh of the electric power that makes 101,3% of a planned task.

Including I was ahead of schedule and It is southern - the Ukrainian nuclear power plant which is in the Nikolaev area. At the plan in 12 282,19 million kWh 12 410,8 kWh are made. The plan target is performed for 101 percent.

And in September as a whole nuclear power plants of the Energoatom national company developed 6,389 billion kWh that makes 97,3% of a planned task. It is thus southern - the Ukrainian nuclear power plant, unlike the majority of stations, for September I was ahead of schedule. At the planned 1 345,1 million kWh 1 350,0 kWh are made. It makes 100,4 percent from the plan.