In Nikolayevshchina by preparation for a heating season labor protection is observed for 95%

Online: {{ reading || 0 }}Read:{{ views || 797 }}Comments:{{ comments || 0 }}    Rating:(478)         

In September - October, 2009 the territorial administration of the Gosgorpromnadzor of the Nikolaev area carried out target inspections at the under control enterprises with a high risk concerning observance of requirements of labor protection during preparation for work in the oseena - the winter period 2009-2010r.

JSC Nikolaev Combined Heat and Power Plant according to the schedule of repairs I executed repair of 4 power and 1 water-heating coppers, and also maintenance of 3 turbogenerators. 35 damages of thermal networks which were revealed after spring hydraulic tests are eliminated. In total for repair campaign 440 m of thermal networks were replaced. However during the complex inspection which has been carried out at the beginning of October, 91 violations concerning labor protection were revealed and are forbidden the robot of 7 coppers, report a press - the center of the Gosgorpromnadzor for the Nikolaev area.

JSC Nikolayevgaz is conducted examination of 968,1 km of gas networks from which it is replaced 1,238 km. It is carried also out reconstruction and repair of 118 buildings of gas - distributive substations and cupboard gas - distributive substations. Work with 82 owners of housing stock concerning the conclusion of contracts for maintenance of gas pipelines is carried out.

In Management on realization of krapleny gas, JSC Ukrgazservice a schedule of performance of actions for preparation for the oseena - to the winter period (the average percent of performance equals 90%) is broken. For violation of terms 9 heads of the enterprises are brought to administrative responsibility.

By the Nikolaev linear office of Gas trunkline operation center from 95 points of actions are executed 83, in a stage of performance 12, with completion of works in October, 2009

By check it was captured elevators, procuring bases and the enterprises for processing of agricultural production. As a whole preparation of the checked enterprises for work in the oseena - the winter period is conducted according to the approved schedules.However at some enterprises seasonal examinations of production buildings and constructions aren't conducted (JSC Lyudmilivsky elevator, JSC Podgorodnyansky elevator, by JSC Oldsiz-Skifiya), didn't carry out measurements of resistance of devices for grounding and adjustment of electroinstallations (JSC Vradeivsky elevator, JSC Hermes, JSC Repairman, PT Impuls), didn't prepare garages for operation during the winter period (JSC Ukr-kom, JSC Kolosivsky elevator, etc.)

On conclusions of experts I rubbed managements of the enterprise of Nikolaev for 95% executed actions for observance of requirements of labor protection during preparation for work in the oseena - the winter period 2009-2010r.