On the first hydrounit of Aleksandrovsky hydroelectric power station passes planned repair

Online: {{ reading || 0 }}Read:{{ views || 935 }}Comments:{{ comments || 0 }}    Rating:(561)         

About work of separate division "It is southern - the Ukrainian nuclear power plant" from August 11 to August 24, 2009

During the period from August 11 to August 24 in the separated division "It is southern - the Ukrainian nuclear power plant" 616 million 907 thousand kilowatts - hours of the electric power are made, including on:

* the nuclear power plant - 610 million 354 thousand kilowatts - hours;

* Tashlyksky pumped storage power plant - 6 million 505 thousand kilowatts - hours;

* Aleksandrovsky hydroelectric power station - 48 thousand kilowatts - hours.

For receiving such quantity of the electric power on a thermal power plant it would be necessary to burn 229 thousand tons of Donetsk coal, or 174 million 343 thousand cubic meter of natural gas.

The first power unit YuU nuclear power plant was in a "cold" reserve.

The equipment of the second and third power unit worked without remarks in the set mode.

On Aleksandrovsky hydroelectric power station in work, depending on a consumption of water in the river the Southern Bug, was the second hydrounit. On the first hydrounit since August 10 planned repair is made.

The first and second hydrounits of Tashlyksky pumped storage power plant worked according to the set schedules of loadings.

Radiation background on an industrial platform It is southern - the Ukrainian nuclear power plant for the specified period I was at the level of natural background values which were measured to start-up of nuclear power plant, and for August 25 makes 10,5 μR/year. Emissions of radioactive materials in environment didn't exceed the established admissible values, reports work department with the public and OP YuU nuclear power plant mass media.

-